BY ROBERT BEHRE
Of The Post and Courier Staff
Charleston Post and Courier—Oct.13, 2003
When the city of Charleston set out to renovate Market Hall
after Hurricane Hugo in 1989, it aimed to set a new standard
for historic preservation.
It was a sensible goal in this case: Not only was this 1841
building heavily damaged by that storm and from decades of
neglect, but in a city full of landmarks, Market Hall stands
out, clearly deserving of careful -- and costly -- attention.
The restoration took 13 years, as architects studied the
building, as the city figured out how to pay for its eventual
$3.6 million cost, and as what was expected to be a two-year
construction phase stretched over 40 months.
Earlier this year, the building reopened with an appearance
much the same as during the Civil War, when would-be soldiers
walked up its sandstone steps to enlist in the Confederate
cause. Today, as vendors bustle around in the open air below,
visitors ascend the same steps to see a century-old museum
full of artifacts from that war.
Did the city succeed in setting a new standard?
Consider:
-- The work included repairing timber beams in the roof that
had rotted from termites and moisture. The contractors brought
in timber guild members from as far away as Massachusetts
and West Virginia to make the repairs while leaving as much
original fabric as possible.
"I think the thing that says the most about the restoration
is not what you see but what you don't see," says Bill
Turner of the city's Parks Department. "We could have
done it cheaper, but we chose to save as many timbers as we
could."
Likewise, it would have been easier to remove all the stucco,
but between 65 and 75 percent was saved, Turner says.
-- Re-pointing the masonry walls, which are at least five
bricks thick, deep inside the structure. Again, the city could
have done it more cheaply -- and this work is invisible, too
-- but it didn't.
"The biggest challenge to start with was getting into
the meat of the job," says Tom McGee of NBM Construction.
"There were more structural problems than we thought,
and we had to almost stop and put more time and effort into
the stabilization of the structure in order to fix it."
-- Reopening the arcade below, which had been closed in with
shops in the 20th century. The work wasn't part of the original
plan, but city officials made the change after ripping out
the shops and savoring the new, open space.
"You can feel the history here," says Parks Director
Steve Livingston while standing underneath. "Like you
were in the 1840s or 1860s with this vaulted space overhead."
The change included the addition of new, generous sidewalks
along both North and South Market streets.
-- Recreated the interior oculus -- or circular skylight
-- based on evidence on the walls. Architect Joseph K. Oppermann
says its design, blending amber and frosted clear glass, was
based on remnants of such glass found inside the building.
-- Sensitively adding an elevator, at the request of advocates
for the handicapped. While many preservation groups and the
state Archives and History Department initially resisted the
lift -- which wasn't required because historic landmarks are
exempt from the Americans with Disabilities Act -- Mayor Joseph
P. Riley Jr. pushed for it anyway.
Today, a transparent ornamental iron cage is tucked inside
the building's arcade and is able to carry a person to the
museum above, where it arrives in a small room off to the
side. Not only is it difficult to see, but it also could be
easily removed.
-- The first use of limewash, a thin, watery mix of lime
and pigments, in the city in perhaps about a century. Both
the exterior and interior colors -- even the controversial,
bright green color on the iron rails -- were based on paint
samples taken from the building itself.
"The rails are just a little bit striking, and some
people think it's too much," Livingston concedes. But
restoring only the parts still considered tasteful by today's
standards would have been an impure --even half-baked -- approach.
-- Finding sandstone from the original quarry to replace
the worn steps out front after the first set of stone steps
were an unsuitable color and after preservation groups rejected
a second set of cast-stone steps.
"We got a lot of pressure, and it was good. That's what
communities do," Livingston says. "They raised our
consciousness above where we were at the time."
-- A painstaking approach to restoring its original colors,
including faux graining on its massive pine doors (repainted
to resemble oak) and on its pine mantels (repainted to resemble
expensive marble). When an investigation showed that the cornice
was originally brown paint mixed with brownstone dust, that
look was recreated, too.
"The building is really all about illusion, a much more
grand space originally than what the budget permitted it to
be," says Oppermann. "There's faux painting and
faux materials and faux spaces. It's a wonderfully designed
building."
People can decide for themselves if a new standard was set,
but the National Trust for Historic Preservation has already
made up its mind: Earlier this month, it gave the city, Oppermann
and NBM Construction Co. its National Preservation Honor Award.
"We are continually pleased by the high standards for
historic preservation set by the city of Charleston,"
Trust president Richard Moe said. "Charleston has long
been revered as a model for historic preservation, and the
painstaking attention to detail exhibited in the restoration
of Market Hall further illustrates Charleston's dedication
to maintaining its historic landmarks."
"We weren't trying to make a building look new,"
Oppermann adds. "What we were trying to do was to conserve
the old. We wanted it to look like an old building well maintained,
and I think all of us are pleased that we did that."
Robert Behre may be reached at 937-5771 or by fax at 937-5579.
His e-mail address is
rbehre@postandcourier.com, and his mailing address is
134 Columbus St. Charleston S.C. 29403.